Vlora TEC close to completion

1 min read
17 years ago
Change font size:

TIRANA, May 08؃ompletion of Vlora TEC is expected within a few weeks. The news was made available by Gjergj Bojaxhi, head of KESH, who inspected work on the project.
“So far, 93 percent of the work has been completed and we expect the TEC to be functional within a few weeks,” said Bojaxhi.
According to KESH, commissioning of the main systems, including the most important element of the project, its turbine, will start within days. Different tests regarding the functionality of the TEC have already been successfully completed.
The Vlora TEC will have a power capacity of 97.167 MGW with a combined cycle of gas and steam. The gas turbine will use D1 quality diesel and natural gas. The technology used on this public work is of the latest generation. 400 foreign and domestic specialist, and 150 Albanian labors will work in the new TEC once it becomes functional.

Latest from Business & Economy

Prof. Dr. Alaa Garad is President and Founding Partner of the Stirling Centre for Strategic Learning and Innovation, University of Stirling Innovation Park, Scotland. He is actively engaged in health tourism, higher education and organisational learning across the Western Balkans, including the Global Health Tourism Leadership Programme in Albania.

Building a Trusted Health Tourism Ecosystem: Albania’s Next Competitive Advantage

Change font size: - + Reset by Professor Alaa Garad Tirana Times, March 17, 2026 – There are countries you visit, and there are countries you remember. Albania is rapidly becoming the
1 month ago
7 mins read